Campus Construction Update

Posted by Stephanie Rogers on June 29, 2017 in News

The Campus Construction Update is a regular feature of the Weekly E-Bulletin in an effort to keep the campus community informed of any potential distruptions to regular work practices during summer construction.

June 26-29th

Remove old windows in section B (Rooms 140, 142, 242, 246)

Prep openings for new window installation in rooms noted above
Miscellaneous joint cutting on exterior of building on daily basis
The classrooms above should be considered closed during this time frame.

July 4th-7th

Install new windows in section B- (rooms 140, 142, 242, 246)
Remove old windows in section C (rooms 254, 255,257, female wash room second floor
All classrooms in section B and C should be considered closed during this time frame.

Thank you for your patience and understanding,