HÂþ»­

 

News

» Go to news main

Campus Construction Update

Posted by Stephanie Rogers on May 15, 2017 in News

The Campus Construction Update will become a regular feature of the Weekly E-Bulletin in an effort to keep the campus community informed of any potential distruptions to regular work practices.

Week of May 15th

Start Piping Install in CHUTE and RUMINANT Buildings. (Chance of minor noise with this work)

Demolition to continue in DAIRY, LANGILLE and HALEY Buildings. (Chance of minor noise with this work)

Isolation and draining to start in HALEY NORTH, HALEY SOUTH, HALEY AQUACULTURE, JENKINS HALL and possibly part of CUMMING HALL. (Note: heating will be shut off in these buildings)

Week of May 23rd

Piping Installation to continue in RUMINANT building and start in BOULDING and DAIRY Buildings. (Chance of minor noise with this work)

Demolition continues in HALEY and JENKINS HALL. (Chance of minor noise with this work)

Any questions or concerns please contact:

Stephanie MacKenzie
Project Manager Facilities Management
902.956.4492
Stephanie.Mackenzie@dal.ca